If you’re among those who heard the work on West Dam stopped in June due to a lack of funding, you heard wrong.
The reasons the work stopped are two that are familiar to Custer—golf and tourism.
Contractors working on the second phase of the project—the removal of 100,000 cubic yards of silt and material out of the reservoir—actually worked a little later into June than initially anticipated, and will resume work earlier as well. Initially the work was to resume in mid-October, but instead will resume in September.